Toyota FJ Cruiser (GSJ 10, 15 series). Instruction — part 373
PS–42
POWER STEERING – POWER STEERING LINK (for 4WD)
PS
15. INSPECT POWER STEERING RACK
(a) Insert a wire 20 mm (0.79 in.) into the vent hole of
the steering rack and ensure that the vent hole is
not clogged with grease.
NOTICE:
If the hole is clogged, the pressure inside the
boot will change after it is assembled and the
steering wheel is turned.
16. INSPECT TIE ROD END SUB-ASSEMBLY LH
(a) Flip the ball joint stud back and forth 5 times as
shown in the illustration, before installing the nut.
(b) Using a torque wrench, turn the nut continuously at
a rate of 2 to 4 seconds per turn and take the torque
reading on the 5th turn.
Torque: (turning)
0.29 to 1.96 N*m (2.96 to 20 kgf*cm, 2.56
to 17.35 in.*lbf)
17. INSPECT TIE ROD END SUB-ASSEMBLY RH
HINT:
Use the same procedures described for the LH side.
18. REMOVE STEERING RACK PISTON RING
(a) Using a screwdriver, remove the "Teflon" ring and
O-ring from the steering rack.
NOTICE:
Be careful not to damage the groove of the ring.
INSPECTION
1.
INSPECT TIE ROD END SUB-ASSEMBLY
(a) Flip the ball joint stud back and forth 5 times as
shown in the illustration before installing the nut.
(b) Using a torque wrench, turn the nut continuously at
a rate of 2 to 4 seconds per turn and check the
torque reading on the 5th turn.
Torque: 0.29 to 1.96 N*m (2.96 to 20 kgf*cm, 2.56
to 17.35 in.*lbf)
2.
INSPECT POWER STEERING RACK
(a) Using a dial indicator, check the power steering rack
for runout, teeth wear and damage.
Maximum runout:
0.3 mm (0.012 in.)
If necessary, replace the power steering link
assembly.
(b) Check the back surface for wear and damage.
If necessary, replace the power steering link
assembly.
G038615E01
ZK08184E02
ZK08184E01
ZX09355E03
POWER STEERING – POWER STEERING LINK (for 4WD)
PS–43
PS
REASSEMBLY
1.
INSTALL STEERING RACK PISTON RING
(a) Coat a new O-ring with power steering fluid and
install it onto the steering rack.
(b) Stretch a new "Teflon" ring with your fingers.
NOTICE:
Be careful not to overstretch the "Teflon" ring.
(c) Coat the "Teflon" ring with power steering fluid.
(d) Install the "Teflon" ring onto the steering rack
groove. Grip the ring to press it into the groove.
2.
INSTALL POWER STEERING RACK
(a) Apply grease onto the rack teeth ends.
(b) Install SST onto the steering rack.
SST
09631-00350
HINT:
If necessary, scrape the burrs off the rack teeth end
and burnish.
(c) Coat SST and the power piston oil seal with power
steering fluid.
(d) Install the steering rack onto the rack housing.
(e) Remove SST.
(f)
Coat SST with power steering fluid.
SST
09631-00350
(g) Install SST onto the steering rack opposite end.
(h) Coat the lip of a new oil seal with power steering
fluid. Using SST, install the oil seal onto the steering
rack.
NOTICE:
•
Slide SST and the oil seal straight without
tilting them.
•
Install the oil seal facing in the correct
direction.
C003629E01
N000401E01
Rack Teeth End
SST
W002101E02
SST
F005044E01
PS–44
POWER STEERING – POWER STEERING LINK (for 4WD)
PS
•
Be careful not to damage the lip of the oil
seal.
(i)
Remove SST.
3.
INSTALL CYLINDER END STOPPER
(a) Apply sealant to the stopper.
(b) Using a wooden block and hammer, tap in the
stopper until it is tightly installed.
Sealant:
Part No. 08833-00080, THREE BOND 1344,
LOCTITE 242 or the equivalent
(c) Using SST, tighten the stopper.
SST
09631-20120
Torque: 145 N*m (1,479 kgf*cm, 107 ft.*lbf)
4.
TEST AIR TIGHTNESS
(a) Install SST to the unions of the rack housing.
SST
09631-12071 (09633-00010)
(b) Apply 53.33 kPa (400 mmHg, 15.75 in.Hg) of
vacuum for about 30 seconds.
(c) Check that there is no change in the vacuum.
If there is a change in the vacuum, check the
installation of the oil seals.
5.
INSTALL POWER STEERING CONTROL VALVE
(a) Apply molybdenum disulfide base grease to the
needle roller bearing inside the rack housing shown
in the illustration.
Volume of grease applied:
Approximately 2 g (0.07 oz)
ZX00351E01
SST
F043535E02
F051732
Grease Filling
G035022E01
POWER STEERING – POWER STEERING LINK (for 4WD)
PS–45
PS
(b) Install the control valve with the 2 bolts.
Torque: 18 N*m (185 kgf*cm, 13 ft.*lbf)
6.
INSTALL RACK GUIDE
(a) Install the rack guide and spring.
(b) Apply sealant to 2 or 3 threads of the rack guide
spring cap.
Sealant:
Part No. 08833-00080, THREE BOND 1344,
LOCTITE 242 or the equivalent
(c) Using a 24 mm hexagon wrench, temporarily install
the spring cap.
7.
ADJUST TOTAL PRELOAD
(a) To prevent the steering rack teeth from damaging
the lip of the oil seal, temporarily install the RH and
LH rack ends.
(b) 2WD:
Using a 24 mm hexagon wrench, tighten the rack
guide spring cap.
Torque: 25 N*m (250 kgf*cm, 18 ft.*lbf)
(c) Loosen the cap 30
°.
(d) Using SST, turn the control valve shaft right and left
1 or 2 times. The rack end will move in and out.
SST
09616-00011
(e) Using a 24 mm hexagon wrench, loosen the cap
until the rack guide spring does not function.
(f)
Using SST, a torque wrench and 24 mm hexagon
wrench, tighten the cap until the preload is within
the specification.
SST
09616-00011
Torque: Preload (turning)
0.8 to 1.6 N*m (8.2 to 16.3 kgf*cm, 7.1 to
14.2 in.*lbf)
NOTICE:
Perform adjustments in the tightening direction
of the spring cap.
G100343E01
24 mm
Hexagon
Wrench
F042802E02
24 mm
Hexagon
Wrench
30°
F043642E02
SST
G100341E01
24 mm
Hexagon
Wrench
SST
F043547E02
Нет комментариевНе стесняйтесь поделиться с нами вашим ценным мнением.
Текст