Chery B14. Manual — part 26

10.1.2 Disassemble front ceiling light (Refer to

disassembly/assembly of front ceiling light)

10.1.3 Disassemble rear ceiling light. (Refer to

disassembly/assembly of rear ceiling light)

10.1.4 Disassemble all the roof handles. (Refer to

disassembly/assembly of roof handle)

10.1.5 Disassemble A/B/C/D pillar protecting board.

(Refer to disassembly/assembly of A/B/C/D pillar

protecting board)

10.1.6 Take away scuttle trimming rubber strip by hand.

10.1.7 Disassemble roof clips (totally10 pieces) by

flat head screwdriver, and take off roof.

10.2 Assembly steps

The installing steps are reverse to those for removal.

3

1

2

4

5

6

7

8

9

10

II. Disassembly of Scuttle Assembly

1 Preparation

Tool: No.10, No.13 and No. 17 socket spanner, clamp pliers

2 Disassembly steps

2.1 Disassemble roof(see disassembly of roof).

2.2 Take off scuttle cable inserting.

2.3 Disassemble scuttle water exhaust pipe by clamp

pliers(totally 4 pieces)

2.4 Loose scuttle fixing bolts. (totally 10 pieces)

Installation torque is 9±1Nm

2.5 Take off scuttle assembly.

3 Assembly steps

The installing steps are reverse to those for removal.

III. Decomposing of Scuttle Assembly

1 Preparation

Tool: Torx5,Torx10,Torx20,cross head screwdriver and flat head screwdriver.

2 Disassembly/assembly of scuttle glass

2.1 Disassembly steps

2.1.1 Operate the scuttle to completely open status.

2.1.2 Take away scuttle trimming strip by pushing

it backwards by hand.

2.1.3 Unscrew the scuttle fixing bolts by cross head

screwdriver (loose two middle screws first and then loose

the other four)

2.1.4 Take off the scuttle glass by hand from the car top.

2.2 Assembly steps

2.2.1 Operate the scuttle switch to move the sliding

mechanism without glass to complete opening position, put

glass into middle of sliding mechanism support bar.

(Note: the side with mark should be on the back)

2.2.2 Fasten scuttle glass six fixing bolts by cross head

screwdriver; first slightly fasten and then pull the glass

forward slightly and then fasten them one by one.

2.2.3 Operate the scuttle switch to move the scuttle to its

complete close status.

2.2.4 Begin to adjust and fasten these middle two fixing

nuts at the same time to drug the glass by hand. Fasten the

other four screws at the same time of move the glass to

correct height.

Torque:

2.2.5 Check the switch program of the scuttle if is correct.

Remarks: after the installation check the glass height/

starting noise and collision phenomenon.

2.2.6 Assemble trim strip after the first time adjustment.

2.2.6.1 Operate the scuttle to completely open status.

2.2.6.2 Block the scuttle trim strip to sliding mechanism

bracket bar by hand.

Была ли эта страница вам полезна?
Да!Нет
9 посетителей считают эту страницу полезной.
Большое спасибо!
Ваше мнение очень важно для нас.

Нет комментариевНе стесняйтесь поделиться с нами вашим ценным мнением.

Текст

Политика конфиденциальности