DAF CF65, CF75, CF85 Series . Manual — part 1066
©
200424
3-3
Inspection and adjustment
HYDRAULIC LIFTING GEAR
ΧΦ65/75/85 series
8
9
5.
Turn the adjusting bolt (1) using an Allen key.
During the adjusting process the trailing axle
should not be activated.
-
Screwing the bolt in will increase the
pressure.
-
Unscrewing the bolt will decrease the
pressure.
Turn the adjusting bolt (1) using small steps
of not more than 20
. Measure the pressure
after each step.
Note:
As the pressure increases very rapidly, a
large turn of the adjusting bolt can result in
excessive system pressure causing
damage.
6.
Lift the trailing axle and take the pressure
reading. Release the control switch on the
dashboard immediately once the maximum
pressure is achieved.
If the pressure exceeds 200 bar, the control
switch on the dashboard should be released
immediately.
7.
If the measured value is still incorrect:
connect the pressure-switch connector
and lower the trailing axle.
8.
Turn the adjusting bolt (1) once again.
9.
Remove the pressure switch connector.
10. Wait for approx. 2.5 minutes and take a new
reading. If necessary, repeat points 7 to 10
until the pressure setting is correct.
11. Tighten lock nut (2). Make sure that the
adjusting bolt (1) does not turn too.
12. Connect the connector of the pressure
switch, lower the trailing axle and check the
pressure again.
13. Remove the T-piece and pressure gauge.
14. Check the oil level in the reservoir and top up
if necessary.
1
2
3
A8 00 279
1
2
3
A8 00 279
HYDRAULIC LIFTING GEAR
3-4
©
200424
Inspection and adjustment
9
ΧΦ65/75/85 series
8
3.3 CHECKING INTERNAL LEAKAGE IN THE PUMP UNIT
1.
Check the setting of the pressure relief valve
before conducting this test.
2.
Lower the trailing axle. The wheels of the
trailing axle must rest on the ground.
3.
Clean pipe connection B of the pump unit.
4.
Remove the pipe from pipe connection B and
plug the pipe.
5.
Connect the pressure gauge, special tool
(DAF no. 0535653), to pipe connection B so
that the pipe connection is also plugged.
6.
Put the control switch into the "lifting"
position. The pressure will quickly increase
and the pressure switch will deactivate the
pump motor. Release the control switch.
7.
Take the pressure reading and check the
outward leakage. Leave the pump unit in
pressurised condition, also depending on the
complaint (how quickly the trailing axle will
be lowered by itself). If the pressure
decreases, the non-return valve in the 2/2
solenoid valve or the gasket of the 2/2
solenoid valve is leaking.
8.
Activate the 2/2 solenoid valve manually
after the test using a 24V power supply. The
2/2 solenoid valve will be activated,
rendering pipe connection B of the pump unit
pressureless.
9.
Remove the pressure gauge and reconnect
the piping.
10. Activate the lifting gear and check the oil
level in the reservoir. Inspect the pipe
connections for leaks.
B
A
A8 00 281
©
200424
3-5
Inspection and adjustment
HYDRAULIC LIFTING GEAR
ΧΦ65/75/85 series
8
9
3.4 BLEEDING OF THE HYDRAULIC LIFTING GEAR
The lifting gear is bled automatically. If
necessary, lift and lower the trailing axle several
times in a row.
The oil level in the reservoir should not fall below
the minimum level.
Note: after lowering the trailing axle, wait approx.
2.5 minutes before lifting the trailing axle.
If the switch is activated before this time span of
approx. 2.5 minutes elapses, the time will be
reset and you will have to wait about another
2.5 minutes before you can lift the trailing axle.
3.5 CHECKING THE FLUID LEVEL IN THE HYDRAULIC LIFTING GEAR
1.
Make sure that the trailing axle wheels are
fully lowered and on the ground.
2.
Check the fluid level. The liquid level must be
between the "min." and "max." level mark. If
necessary, top up.
HYDRAULIC LIFTING GEAR
3-6
©
200424
Inspection and adjustment
9
ΧΦ65/75/85 series
8
3.6 CHECKING THE CYLINDER
1.
After cylinder disassembly and assembly the
cylinder should be checked for internal and
external damage. See "Disassembly and
assembly".
2.
Pull the entire length of the piston rod out of
the cylinder.
3.
Connect a test pump with pressure gauge to
pipe connection B. Both pump and pressure
gauge should be able to handle a minimum
pressure of 220 bar.
4.
Increase the pressure to the prescribed test
pressure, see "Technical data" and leave the
cylinder pressurised for some time.
Never stand in front of the piston rod when
increasing the pressure. If the spring clip (6)
is not installed correctly, the piston rod could
come out of the cylinder.
5.
Check the cylinder for internal and external
leakage.
6.
Push the piston rod completely into the
cylinder and plug the pipe connections after
completion of the test.
1 2
1
2
11 12
13 14 15 16 17 18
3 4 5 6
8 9
A
B
10
7
A8 00 248
B
A
A8 00 281