Ford Ranger EV (2001 year). Manual — part 128
414-03A-108
414-03A-108
High Voltage/Traction Battery
REMOVAL AND INSTALLATION (Continued)
3.
WARNING: The nominal voltage of
the traction battery is 312 volts. The buffer
zone must be set up and insulated rubber
gloves and a face shield must be worn.
Failure to follow these precautions may
result in severe personal injury or death.
Observe the EV-specific precautions. Refer to
1 Set up the buffer zone.
2 Test and wear the insulated rubber gloves.
3 Wear the face shield.
4. Pull the connectors from the top of the
contactor box.
5. Open the contactor box.
1 Remove the four screws.
2 Open the contactor box.
6. Use a fuse puller to remove the necessary fuse.
1 25A Charger Fuse
2 10A Heater Fuse
3 40A Auxiliary Fuse
414-03A-109
414-03A-109
High Voltage/Traction Battery
REMOVAL AND INSTALLATION (Continued)
Installation
1. To install, reverse the removal procedure.
•
Apply Locktite 242 to the 22 traction
battery cover bolts.
HVPDB Fuses
Removal
1. Disconnect the traction battery auxiliary load
high-voltage connector. Refer to
2. Remove the high-voltage power distribution box
(HVPDB) cover.
1 Remove the four screws.
2 Remove the cover.
414-03A-110
414-03A-110
High Voltage/Traction Battery
REMOVAL AND INSTALLATION (Continued)
3. Remove the HVPDB fuse safety cover.
1 Remove the two screws.
2 Remove the cover.
4. Use a fuse puller to remove the necessary fuse.
1 10A Power Steering Fuse
2 25A Positive Temperature Coefficient (PTC)
Heater Fuse
3 25A A/C Fuse
4 10A DC/DC Fuse
Installation
1. To install, reverse the removal procedure.
414-03A-111
414-03A-111
High Voltage/Traction Battery
REMOVAL AND INSTALLATION (Continued)
High Voltage Power Distribution Box (HVPDB)
Removal
1. Remove the positive temperature coefficient
(PTC) module. Refer to
2. Disconnect the power steering pump electrical
connector.
3. Disconnect the electrical connectors.